Rajshahi, Nov 18 (V7N) – Allegations of large-scale sand and fertile soil extraction from six designated areas along the Padma River in Godagari upazila of Rajshahi have raised concerns over the safety of the Sultanganj river port and surrounding settlements.
The Sultanganj river port, located at the confluence of the Padma and Mahananda rivers, has an established waterway connection with the Maya river port in West Bengal, India. Import and export trade between Bangladesh and India through the Sultanganj-Maya route began on February 12, 2024, and port operations remain active.
The Bangladesh Inland Water Transport Authority (BIWTA) has designated a 20-kilometre stretch of the river, covering upstream and downstream areas around the port, as part of its jurisdiction. BIWTA is responsible for safeguarding the port area.
Considering sand extraction from the river within the port boundary risky, BIWTA had asked the Ministry of Shipping, the Ministry of Land and the Rajshahi district administration to stop the leasing process for the sand quarry. Subsequently, the district administration and the District Sand and Soil Management Committee cancelled the lease of the six-mouza sand quarry in Godagari this year and declared it permanently closed.
However, despite the closure, allegations have emerged that the former leaseholder, Abdul Mannaf, owner of Mam Enterprise, has continued extracting sand and soil from the river and its banks.
A field visit reportedly found excavators removing fertile alluvial soil from extensive riverside areas following the recession of floodwaters. Dredgers are also allegedly extracting large quantities of sand from a 10-kilometre stretch between Sultanganj upstream and Phultala downstream.
Large stockpiles of sand have reportedly been accumulated beside the highway in Sultanganj, Sarangpur, Faridpur, Bidirpur and Premtali. Excavators are being used to load the materials onto dump trucks, trucks and other vehicles for transportation to different parts of the country.
Local residents allege that fertile silt deposited by the river has raised agricultural land along the banks, including areas around Biyanabana, Premtali, Bidirpur, Phultala, Rail Bazar, Hatpara and Sultanganj. Many families had planned to cultivate crops on the newly deposited soil, but claim that the land has been excavated over the past two months.
Residents further allege that sand is being removed daily from four or five locations, including Phultala, while more than 100 trucks transport soil from the area. They have questioned how the former leaseholder has been able to deploy excavators and dredgers and continue operations around the clock despite the quarry's closure.
Local residents also alleged that the former leaseholder continued extracting sand illegally for about three months after the expiry of the previous lease last year. They have demanded an immediate halt to the activities and an investigation into the legal basis for the ongoing extraction.
According to information obtained during the investigation, Abdul Mannaf filed a writ petition with the High Court in July, claiming that he had suffered losses. On August 6, a High Court bench reportedly allowed him to operate the sand quarry for three months.
The order was initially due to expire on November 6. However, the former leaseholder subsequently obtained an extension of the order, allowing the extraction activities to continue.
District administration sources said that after receiving a copy of the first court order, Rajshahi Deputy Commissioner Kazi Shahidul Islam, also chairman of the District Sand and Soil Management Committee, sent an urgent letter on September 7 to the Ministry of Shipping, the Ministry of Land, the BIWTA chairman and the Solicitor Wing of the Ministry of Law, Justice and Parliamentary Affairs.
In the letter, the deputy commissioner stated that the former leaseholder's contractual rights over the quarry had ended on April 14, 2025, corresponding to the final day of the Bengali year 1433, according to the administration's account. He said the lease agreement did not provide the former leaseholder with any continuing rights after the contract expired.
The deputy commissioner urged the relevant authorities to promptly file an appeal against the High Court order.
However, sources alleged that although BIWTA decided to challenge the order, the appeal was delayed following intervention by a political leader from Rajshahi. According to the allegations, the leader visited BIWTA headquarters late last month and pressured officials not to file the appeal.
The delay reportedly allowed the former leaseholder to obtain a subsequent order through a hearing in which the authorities did not effectively contest the matter. These allegations could not be independently verified.
Shariful Islam, a resident of the six-mouza sand quarry area, said the former leaseholder had continued removing sand and soil for three months after the previous lease expired last year.
When contacted, Rajshahi Additional Deputy Commissioner (Revenue) Md Belayet Hossain said the district administration had requested the Solicitor Wing of the Ministry of Law and BIWTA officials to take necessary legal steps immediately after receiving the first court order.
"We do not know why the authorities are delaying the filing of an appeal," he said.
He added that the District Sand and Soil Management Committee had abolished the sand quarry and that the district administration no longer had direct control over it. BIWTA is now the custodian of the area, he said.
BIWTA member and Joint Secretary (Planning and Operations) Md Sajedur Rahman said a decision had been taken to appeal against the High Court order and that the necessary documents had been prepared.
"The appeal will be filed as soon as possible," he said.
Responding to allegations that he had concealed details of the lease agreement and obtained court orders to continue operating the quarry, former leaseholder Abdul Mannaf said he was carrying out the activities under a court order. He claimed that the High Court had permitted him to extract and transport sand and conduct other related operations.
Meanwhile, residents and concerned citizens have warned that continued sand extraction could intensify riverbank erosion and threaten embankments, homes, mosques, deep tube wells, roads, agricultural land and shops along the Padma.
They have urged the authorities to immediately stop the extraction and take effective measures to protect the riverbanks, local communities and the Sultanganj river port.
END/MRA/SMA/